The question

What does a cost per unit have to have before it means anything?

A total is a number about one system. A unit cost is a claim that can be compared: against a supplier, against last year, against another team. Comparison is the point of computing one. A unit cost that is not comparable is worse than no unit cost, because it will be compared anyway.

The material

Two divisions: a quantity and a period

Unit economics. Working out what something costs you per unit, where the denominator is counted over a stated period: cost per terabyte-month, cost per million requests. The quantity must be one you can defend and measure consistently.

A unit cost is a total divided by a quantity. This fleet produces two unit costs from the same money, and the trap sits in a different place in each.

For the cost per stored terabyte, the quantity is itself a stock: terabytes held at one moment, with no period built in. A cost per stored terabyte needs a period added — per terabyte-month or per terabyte-year, and that second division is where the trap sits for storage. Per terabyte-month and per terabyte-year differ by a factor of twelve, and on a slide they look equally authoritative. Problem 17.1 is that arithmetic. In a model file, the toolkit catches it: the two units have the same dimensions and different sizes, and the toolkit converts between them.

This model’s own unit cost is an example where its formula divides by a horizon in years and the node declares its unit per month, so the build applies the factor of twelve. Appendix D lists that conversion and notes that a check comparing dimensions alone would miss an error of that magnitude. On a slide, nothing catches it.

For the cost per million requests, the period is already inside the denominator: a rate, times how long it ran. So the trap moves. Was the rate the busy hour or the mean? The two differ by the ratio ch04 put in the model. A cost per request quoted against the busy hour is several times the same cost quoted against the mean, and both describe the same fleet.

The denominator hides two choices

Take one model, one set of samples, one five-year total, and ask for a cost per stored terabyte per month. The denominator hides two separate choices, and each has more than one defensible answer. The first choice is when in the fleet’s life you count what is held: on day one, at the horizon, or as an average over the years between. The second choice is the order: divide each future’s total by that same future’s holding and then take the median, or take the median total and the median holding first, and divide one by the other. Problem 17.2 computes four combinations:

They are not close together. What is held at the horizon is what is held on day one, compounded over five years by the annual growth factor, so most of the gap between the four is the first choice: day one against the rest. Problem 17.2 shows you how far apart they are.

The second choice is about what the figure means. Dividing first keeps each future’s total over that same future’s holding. Taking medians first sets a total from one set of futures over a holding from another, so the result describes no single future.

The model’s own denominator

The model’s own cost per stored terabyte-month is a fifth combination, using the straight-line average and dividing first. Each future’s total goes over the straight line between day one’s holding and that future’s own horizon holding, per month. The median printed on the cost-per-stored-terabyte chart further down this page is that fifth figure. The model states its choice in the node’s note:

  average_stored:
    kind: derived
    unit: TB
    note: >-
      It is the mean of the day-one and horizon holdings: a straight line between the two ends of
      the horizon. The holding compounds, so the curve bends upward and the line lies above it,
      overstating what is held on average. Cost per stored terabyte-month comes out low, more so the
      faster growth is; ch17 shows by how much. It follows the same convention as the mean request
      rate, for the same reason: the exact average becomes zero divided by zero when there is no
      growth.
    formula: (stored_data_t0 + stored_data) / 2

  cost_per_stored_tb_month:
    kind: derived
    unit: USD/TB/month
    label: cost per stored TB per month
    note: >-
      In each future, it divides that future's total by that future's straight-line holding, so it
      is neither a ratio of two middle values nor a denominator from ch17's problems. It divides by
      a horizon in years and is declared in months. Identical dimensions, a factor of twelve apart,
      so a check comparing only dimensions would publish a figure twelve times too large and pass.
      The build converts, and Appendix D lists the conversion.
    formula: tco / average_stored / horizon

The holding compounds, so its curve bends upward, and the straight line between its two ends lies above the curve everywhere in between. So the straight-line average overstates what is held on average, and a larger denominator gives a smaller unit cost: the straight line flatters the figure. The faster the growth, the larger the overstatement, as this table shows across the three growth factors from the model’s own band for annual growth: its p10, its median and its p90.

Annual growth factorHeld at the horizon (times day one)Straight-line average (times day one)Compounding average (times day one)Straight line too high by
p10, 1.12x1.76x1.38x1.353%
median, 1.34x4.30x2.65x2.2617%
p90, 1.60x10.5x5.74x4.0442%

Source — models/web_service/model.yaml: the growth factor’s declared p10 and p90, and the horizon

The request side has the same straight line. The mean request rate over the horizon is the average of the day-one and horizon mean rates. So it overstates the requests served in the same proportion as the holding, for the same growth, and the cost per million requests is flattered by the same amount.

The model keeps the straight line for two reasons. First, its error runs one way. For steady growth at any rate the straight line never falls below the compounding average, so the model’s unit cost can only err low, and you know which way to correct it. Second, the exact average of a compounding holding needs a logarithm of the growth, and with no growth it becomes zero divided by zero. No growth is the bottom of the range the growth factor’s slider allows, and a formula in the model file cannot branch around it. The model states the convention and its direction rather than hiding it, because a unit cost is only as defensible as its denominator.

Why the unit cost has a wide interval

A unit cost falls when growth arrives. The fleet is fixed: the number of hosts is the decision you took in ch12, so the five-year total does not move when growth does. If the growth turns up, the fleet serves the requests it was bought for, and the cost per million of them is low. If it does not, you have paid for hosts nobody kept busy, and the same fleet is expensive per request.

The chart shows how wide the cost per million requests is across the model’s futures. The width is not measurement error: it is the model saying that the unit cost of a fleet depends on something that has not happened yet. Most of the uncertainty is in the denominator, not in the numerator: the inputs that move the unit cost most change only the requests served.

InputKindcost per million requests at its p10at its p90Swing
annual growth factorinput$3.49$0.84$2.65
peak request rate, day oneinput$3.05$1.16$1.88
peak-to-mean ratioinput$1.34$2.42$1.08
engineers, full-time equivalentinput$1.58$2.15$0.57
licence per coreinput$1.66$2.14$0.47
fully loaded salaryinput$1.64$2.05$0.41
host priceinput$1.66$2.05$0.39
support rateinput$1.77$1.89$0.12

Source — web_service-reference · the model to explore; each input with a range has a slider

The tornado shows the direction. The annual growth factor is at the top. At its p10, low growth, it gives the highest cost per million requests in the table; at its p90, high growth, the lowest. That is why a unit cost quoted without a date is quoting a guess about the future. The busy hour on day one and the peak-to-mean ratio come next, and both change only how many requests are served. The peak-to-mean row runs the other way: a higher ratio means a lower mean rate for the same busy hour, so fewer requests and a higher cost per million. The cost inputs sit below those three: engineers, licences, salary, host price, support.

The same total over the other denominator this fleet carries, the records it holds, is a different unit cost. Its spread is narrower in proportion to its median. You can see it by comparing the two charts’ subtitles. The reason: its denominator moves with the growth factor alone, because day one’s holding is one fixed number. The request denominator also carries the busy hour on day one and the peak-to-mean ratio:

Same money, same futures. One figure is what the fleet costs per unit of the work it does. The other is what it costs per unit of what it keeps. A service that is mostly compute looks expensive by the second measure and cheap by the first. Neither is the cost of anything. Each is the answer to a question, and the question has to travel with it.

What makes a unit cost comparable

A unit cost can be compared with another only when three things about it are stated: its period, what its denominator counts, and what its numerator includes. Missing any one, it cannot be compared with anything.

The period. Per month or per year, written next to the figure. A cost per terabyte with no period can be out by twelve (the first section of this page).

The denominator’s definition. This hides multiple choices: requests or terabytes; the busy hour or the mean; day one, the horizon or an average between; before or after replication. Two organisations comparing “cost per request” can be comparing different requests without either knowing, because neither figure says which it used.

What is in the numerator. People or not; network or not; the building or not. A supplier’s figure includes their margin and excludes your staff. An internal figure usually does the reverse.

This model’s cost per stored terabyte-month states all three. The period is in the node’s declared unit, per terabyte per month. The denominator is in average_stored’s formula and note, quoted under The model’s own denominator, earlier on this page, and in day one’s holding, whose source says it counts the records before replication, indexes or compression. The numerator appears in the formulas that build the five-year total: hosts, network, electricity including the building’s power overhead, licences, support, staff and the cost of moving to the design. Nothing for the building itself beyond its power. Appendix E lists every one of those formulas, and where each input came from. A unit cost stated that way survives being quoted by somebody who was not there.

What a unit cost is for

Not for deciding. A unit cost is a comparison, and comparisons are how you find the question worth asking. A unit cost that is out of line with a supplier’s is a reason to find out why. It is not a reason to buy from the supplier.

The decision needs the total, the risk, and what the alternatives would cost. That is ch21. A unit cost is what gets you invited to that meeting.

What this cannot tell you

Whether the comparison is like for like. Everything above makes this model’s figure explicit. It does nothing about the figure it is being compared against. That figure has its own conventions, and will not state them.

What the right denominator is. The four in problem 17.2 are all defensible, and this book’s model uses a fifth combination, the straight-line average divided first. There is no fact of the matter. There is only a convention, stated or unstated, and this book’s position is that stating it is the discipline.

What the structure omits. A unit cost inherits every missing line from the total it comes from (ch15). Dividing by a large denominator makes a missing line look smaller, not more visible. ch20 teaches how to look for a line the total does not have, an error no amount of sampling can see.

Anything about marginal cost. Every figure here is an average: total over quantity. What the next million requests cost is a different number. The next million requests cost nothing until the fleet runs out of room, and then they cost a whole host, because hosts are bought whole. An average spreads that step evenly over every request, so no average can express it.

Key takeaways

  • A unit cost is a total divided by a quantity, and the trap is in the division. Per month and per year differ by a factor of twelve. The busy hour and the mean differ by the peak-to-mean ratio. Both look equally authoritative on a slide.

  • The denominator hides two choices: when in the fleet’s life you count what is held, and whether you divide before or after taking the median. At least four defensible combinations exist for the same total, they are not close together, mostly because growth separates day one from the horizon, and only dividing first puts the same future above and below the line.

  • A straight line between day one and the horizon flatters a unit cost. A compounding holding curves upward, so the straight line overstates what is held on average and the unit cost comes out low. The faster the growth, the more it flatters. The model keeps it and says so, because the error runs one way.

  • The unit cost of a fleet depends on a future that has not happened yet. If the growth arrives, the fleet is cheap per request. If it does not, the same fleet is expensive. Most of the interval is in the denominator.

  • A unit cost is comparable only with its period, its denominator’s definition and its numerator’s contents stated. Two organisations comparing cost per request can be comparing different requests without either knowing, because neither figure says which it used.

  • A unit cost finds the question worth asking. It does not decide. The decision needs the total, the risk, and what the alternatives would cost.

Problems

Three problems are on this page. The first two have tests, in tests/unit_economics/. The third has no test.

17.1 — A total, a quantity, a period. Divide the total by the quantity and then by the period in months. If your answer is out by twelve, one of you is working in years. If it is out by the number of months in the horizon, you have divided only once.

tests/unit_economics/stubs.py · unit_costyours to edit
def unit_cost(total: float, quantity: float, months: float) -> float:
    """Problem 17.1 - a total, over a quantity, over a period.

    Return the cost per unit per month.

    ``total`` is the five-year total, in dollars. It takes two divisions: by
    the quantity (what is held in terabytes), and by the months (the period
    the total covers). The second division makes it a problem. A cost per terabyte cannot be compared with anything until it
    says per terabyte *per what*. Per TB-month and per TB-year differ by a
    factor of twelve and look equally authoritative.

    In a model file the build catches this: the two units have the same
    dimensions and different sizes, and the build converts. Appendix D lists
    this model's own case. On a slide nothing catches it.
    """
    raise NotImplementedError("problem 17.1")

The same check at a desk: python3 -m pytest tests/unit_economics/test_problem_1_unit_cost.py -m problem

17.2 — Four defensible denominators. The test hands you the five-year totals and what is held at the horizon, sample by sample, with day one’s holding and the months in the horizon. Compute all four and look at the spread. Then set them beside the model’s own figure, the median on the cost-per-stored-terabyte chart above, which is none of the four. Then decide which you would put on a slide, and whether you would be willing to say which it was.

tests/unit_economics/stubs.py · denominatorsyours to edit
def denominators(
    stored_samples: np.ndarray, total_samples: np.ndarray, stored_at_start: float, months: float
) -> dict[str, float]:
    """Problem 17.2 - the same cost, over four defensible denominators.

    You have a bag of five-year totals and a bag of what the service holds at
    the horizon, sample by sample, and two plain numbers the test takes from
    the model: ``stored_at_start``, what it holds on day one, and ``months``,
    the months in the horizon. Somebody wants a cost per terabyte per month.
    Return a dictionary with four of them, keyed exactly as below, each a
    single number. Every one is per month: divide by ``months``.

    Each key makes two choices: when in the fleet's life you count what is
    held (day one, the horizon, or the straight-line average of the two), and
    whether you take medians first or divide first.

    ``"at_horizon"``
        Median total over the median of what is held at the horizon. What you
        will be paying for at the end.
    ``"at_start"``
        Median total over what is held on day one, ``stored_at_start``. What
        you are paying for now.
    ``"average_linear"``
        Median total over the mean of ``stored_at_start`` and the median of
        what is held at the horizon: a straight line between the two ends.
        Holdings compound, so the curve bends upward and the straight line
        lies above it; this average overstates what is held.
    ``"per_sample"``
        Divide each total by what that same sample holds at the horizon, then
        take the median of those ratios.

    All four are defensible and not close together. Only ``"per_sample"``
    divides first, so only it keeps each future's total over that same
    future's holding. ``"at_horizon"`` and ``"average_linear"`` set a total
    from one set of futures over a holding from another. ``"at_start"``
    divides by one number, the same in every future. The model's own
    ``cost_per_stored_tb_month`` is none of the four: it divides first, over
    the straight-line holding.

    Return them, look at the spread, and then decide which you would put on a
    slide - and whether you would be willing to say which it was.
    """
    raise NotImplementedError("problem 17.2")

The same check at a desk: python3 -m pytest tests/unit_economics/test_problem_2_denominators.py -m problem

17.3 — Your denominator, and who chose it. No test: the denominator is a choice, and there is no right one to check it against.

Work out your own cost per unit, then interrogate the denominator. Per terabyte stored, per terabyte ingested, per request, per user, per team: all defensible, all different numbers. Find out when the denominator was chosen, and by whom.

Then find out what the figure is used for. A unit cost quoted in a budget meeting and a unit cost used to decide whether to build or buy need different denominators. Check whether one figure is serving both.

A good answer gives the figure, its denominator, its period, what its numerator includes, who chose the denominator and what the figure is used for. If you divide the total by the denominator and the period you named and do not get the figure you started from, the denominator you were told is not the one that was used, and the answer has to start again from the one that was. A second way to be wrong: the person you name as having chosen the denominator did not choose it, they inherited it. Keep going back until you find a decision, or a record that nobody made one. If the denominator turns out to have been chosen because it made an earlier comparison look favourable, you have found something worth more than the number.

Where to go next

ch18 is what happens when a unit cost from one model becomes an input to another.

ch19 is the question the tornado above keeps raising.