Apply the methodLesson 32 of 76 · 8 min
How much contingency is enough?
Choose a budget reserve using an explicit target and cost distribution.
A contingency reserve is meaningful only relative to a baseline budget and a target outcome. A reserve chosen to cover 90% of modelled costs differs from a reserve based on expected cost or the largest trial observed.
This example combines uncertain labour hours, a fixed hourly rate and an uncertain materials quote. The quantities and prices are invented. One trial must retain its own labour and materials draws before the costs are added.
P90 total cost minus the stated baseline gives the additional amount needed for a 90% modelled cost threshold, floored at zero if the baseline already exceeds P90. This is an outcome quantile, not a confidence interval. Its numerical precision and the credibility of the cost assumptions still need checking.
Is the maximum observed cost a stable definition of a 90% contingency reserve?
Write a prediction (optional)
Seeded teaching simulation
Select Run Python below with the code unchanged.
A saved draft is open. To run the published example, open Tools and select Restore example. Recover draft brings your code back.
Execution error
Technical error details
Your result
Published example output
This result comes from the original Python. Your runs appear above. Build environment ↗
Mean / P90 cost (£): 2517.36 2968.1 Baseline budget (£): 2500 Additional reserve to model P90 (£): 468.1 Estimated P(over baseline): 0.4875
Read the first result
The baseline and chosen coverage target are decision inputs. Different targets legitimately produce different reserves.
Try an edit
At the end of the editor, add this loop on two lines. Start with for coverage in [.8, .9, .95]:. On the next line, indent four spaces and enter print("Coverage:", coverage, "Reserve (£):", round(max(0, np.quantile(total_cost, coverage)-baseline), 2)). Select Run Python again. Compare Reserve (£) across the three Coverage rows. What extra reserve buys a higher coverage target in the same trial costs?
Scope. This teaching model omits dependencies, inflation and changes in scope. No actual budget has been estimated.
Try a fresh case
A reserve is said to “cover uncertainty”. What specification is still needed?
Need a hint?
Hint 1
Ask what counts as total cost.
Hint 2
State the baseline and tolerated overrun probability.