Apply the methodLesson 32 of 76 · 8 min

How much contingency is enough?

Choose a budget reserve using an explicit target and cost distribution.

A contingency reserve is meaningful only relative to a baseline budget and a target outcome. A reserve chosen to cover 90% of modelled costs differs from a reserve based on expected cost or the largest trial observed.

This example combines uncertain labour hours, a fixed hourly rate and an uncertain materials quote. The quantities and prices are invented. One trial must retain its own labour and materials draws before the costs are added.

P90 total cost minus the stated baseline gives the additional amount needed for a 90% modelled cost threshold, floored at zero if the baseline already exceeds P90. This is an outcome quantile, not a confidence interval. Its numerical precision and the credibility of the cost assumptions still need checking.

A reserve follows a coverage target
1.5k2.1k2.6k3.2k3.7k06041.2k1.8k2.4kReference drawsTotal cost (£)
1.5k2.1k2.6k3.2k3.7k06041.2k1.8k2.4kReference drawsTotal cost (£)
Reference illustration. Published cost model. The marked baseline is £2,500; the reserve calculation instead targets its P90. Neither the baseline nor the chosen coverage target is learned automatically from the simulated draws.

Is the maximum observed cost a stable definition of a 90% contingency reserve?

Write a prediction (optional)

Seeded teaching simulation

Select Run Python below with the code unchanged.

Tools
About Python ↗

The code is editable. Press Ctrl+Enter or ⌘+Enter to run Python from the editor.

Published example output

This result comes from the original Python. Your runs appear above. Build environment ↗

Mean / P90 cost (£): 2517.36 2968.1
Baseline budget (£): 2500
Additional reserve to model P90 (£): 468.1
Estimated P(over baseline): 0.4875

Read the first result

The baseline and chosen coverage target are decision inputs. Different targets legitimately produce different reserves.

Try an edit

At the end of the editor, add this loop on two lines. Start with for coverage in [.8, .9, .95]:. On the next line, indent four spaces and enter print("Coverage:", coverage, "Reserve (£):", round(max(0, np.quantile(total_cost, coverage)-baseline), 2)). Select Run Python again. Compare Reserve (£) across the three Coverage rows. What extra reserve buys a higher coverage target in the same trial costs?

Back to the Python editor

Scope. This teaching model omits dependencies, inflation and changes in scope. No actual budget has been estimated.

Try a fresh case

A reserve is said to “cover uncertainty”. What specification is still needed?

Choose an answer
Need a hint?
Hint 1

Ask what counts as total cost.

Hint 2

State the baseline and tolerated overrun probability.